Construction is in full swing. Here are few pics of the under-construction project.
Following is the budget for the Second Phase of development work at Shri Vishwamata Sewashram Jaigaon.
Estimate of development work (roofing of nearly 3500 Sq.Ft. 2nd Phase RCC)
Sl No. | Item | Cost in Rs. |
Iron Rod | 12 mm, 10mm, 8mm (One Ton Each) @Rs.41/- including Transportation | 1,25,000.00 |
Cement | 200 Bags @ Rs. 250/- | 50,000/- |
Sand | 4 Truck @ Rs. 1500/- | 6,000/- |
Chips | 3 Truck @ Rs. 3500/- | 10,500/- |
Chips | 1 Truck @ Rs. 5500/- | 5,500/- |
Mason & Labor | @ Rs. 21/- | 75,000/- |
Misc | Binding Wire- 25Kg @ Rs. 60/- | 1,500/- |
| Plastic 20 Kg @ Rs. 60/- | 1,200/- |
| Feeding labourers | 2,000/- |
Total | | 2,76,700/- |
Rupees Two Lacs seventy six thousand, sevenhundred only/-
|
ACADEMIC GOOD NEWS : Five of our children with disabilities woul be appearing for class 10 exam from NIOS during this year.
Those who want to support, may kindly deposit the amount in bank as per following details:
Develop India Trust A/C DILODIMAG
31793114902
State Bank of India, Hasimara Branch, Jalpaiguri District, West Bengal
(Branch Code 1447)
We wish all our members, supporters and beneficiaries warmest greetings of Durga Puja!
Kind Regards
Construction Committee
Dooars Institute for the Disabled, Jaigaon